HSE says site perimeter fencing should be the main way of keeping people off a scaffold. Taking ladders away at the end of each shift usually works better than a ladder guard. Any ladder guard must be locked or padlocked in place.
Scaffold fans, or sheeting on the lifts, can also put people off climbing. HSE advises against tubes on the first lift that stick out and could be used as footholds. Signs alone are unlikely to stop children.
Sources: HSE: Preventing unauthorised access onto scaffolding and other work platforms
B3 terms
Base plate
Scaffold components
A flat plate at the foot of each upright that spreads the load on to the ground or sole board. Adjustable base plates level a scaffold on a slope.
Base plate: Full definition
Scaffold and tower uprights usually stand on base plates, or on castors if the tower moves. Adjustable base plates sit on a threaded leg, so each upright can be set to the right height on sloping or uneven ground.
The adjustment is for levelling only. It should be kept as short as possible and never used to gain extra height. HSE says a tower must never be propped up on bricks or building blocks.
Sources: PASMA: Operator's Code of Practice, HSE: Tower scaffolds
Birdcage scaffold
Types of scaffold
A scaffold that fills an area with uprights to hold one wide working platform, used to reach high ceilings and other large areas.
Birdcage scaffold: Full definition · used on 1 page
A birdcage gives a wide, stable platform over a large or hard-to-reach area. HAKI notes that a birdcage does not need anchoring to a wall, but it does need a stable foundation.
Interior and exterior birdcages are standard structures in the NASC's TG20:21 Operational Guide.
Sources: HAKI: HAKI Universal Scaffold, NASC: TG20:21 Operational Guide
Brace
Scaffold components
A tube or frame part, often fitted diagonally, that stiffens a scaffold so it cannot sway or buckle.
Brace: Full definition · used on 1 page
Braces lock the uprights and horizontal members into a rigid structure. On a mobile tower they come as diagonal and horizontal braces that hook on to the frames.
HSE notes that rakers, the sloping props sometimes used to steady a scaffold, only work when they are braced and properly footed. A single raker tube on its own is likely to buckle.
C9 terms
CDM Regulations 2015
Safety and regulations
The Construction (Design and Management) Regulations 2015, which set out who is responsible for health and safety on a building project.
CDM Regulations 2015: Full definition · used on 1 page
CDM 2015 gives duties to clients, designers, principal designers, principal contractors, contractors and workers.
Homeowners having work done on their own home are domestic clients. On a job with one contractor, that contractor takes on the client duties. With more than one contractor, the principal contractor takes them on, unless the homeowner agrees in writing for a designer to do so.
Sources: HSE: The Construction (Design and Management) Regulations 2015, HSE: Domestic clients: roles and responsibilities
CHAS
Safety and regulations
A health and safety assessment scheme for contractors, and a founder member of SSIP.
CHAS: Full definition
CHAS certification shows that a contractor has been assessed against recognised standards, including SSIP. Contractors use it to pre-qualify for work with clients.
Sources: CHAS: The UK Leader in Compliance & Risk Management
Chimney scaffold
Types of scaffold
A scaffold that puts a guarded working platform around a chimney stack, for repairs such as repointing or rebuilding.
Chimney scaffold: Full definition · used on 4 pages
Chimney stack scaffolds are one of the standard structures in the NASC's TG20:21 Operational Guide. A chimney scaffold outside those standard set-ups needs its own design.
Work on a sloping roof also needs protection at the roof edge. HSE says edge protection must be fitted at the eaves, and on terraced houses at the back as well as the front. See our residential scaffolding page.
Sources: NASC: TG20:21 Operational Guide, HSE: Roof work, HSE: Scaffolds
CISRS
Cards and qualifications
The Construction Industry Scaffolders Record Scheme, which sets the training and issues the cards for scaffolders in the UK.
CISRS: Full definition · used on 19 pages
CISRS sets the training route from labourer to trainee, scaffolder and advanced scaffolder. It also has cards for scaffold inspection and for supervisors and managers. Most cards last five years. Scaffolder and Advanced Scaffolder cards are renewed with a CISRS CPD course and a valid CITB HS&E test.
CISRS plans to rename itself the Competence In Scaffolding Record Scheme from 1 January 2027. It also plans to leave CSCS on 1 June 2027. Cards issued after that will not carry the CSCS logo, and existing cards stay valid until they expire.
See our careers page.
Sources: CISRS: CISRS Cards, CISRS: FAQs, NASC: CISRS Announces CSCS Licence Termination to Ensure Inclusive Working Practices
CISRS Advanced Scaffolder
Cards and qualifications
The CISRS card for experienced scaffolders, who can lead a gang on all scaffold work, including complex designed structures.
CISRS Advanced Scaffolder: Full definition · used on 7 pages
To take the Advanced course, a scaffolder must have held a Scaffolder (Tube & Fitting) card for at least 12 months. The card also needs an NVQ Level 3, a two-day skills test and a CITB HS&E test from the last two years.
HSE notes that complex structures usually need an Advanced Scaffolder, or someone trained on the specific system scaffold. See our careers page.
Sources: CISRS: Advanced Scaffolder, HSE: Scaffolds
CISRS Part 1
Cards and qualifications
The first CISRS scaffolding course for trainee scaffolders.
CISRS Part 1: Full definition · used on 8 pages
Before Part 1, a trainee must have held a CISRS Labourer card for at least three months and gained relevant site experience. Part 1 includes training on mobile access towers.
Trainees then complete Part 2, an NVQ Level 2 and a one-day skills test, all within two 18-month Trainee Scaffolder cards. Until they qualify, they work under the direct supervision of a qualified scaffolder. See our careers page.
Sources: CISRS: Trainee Scaffolder, NASC: Guide to Appointing a Scaffolding Contractor
CISRS Part 2
Cards and qualifications
The second CISRS course for trainee scaffolders, taken after Part 1 on the way to the Scaffolder card.
CISRS Part 2: Full definition · used on 8 pages
After Part 2, a trainee needs an NVQ Level 2 and the CISRS one-day skills test. With a CITB HS&E test from the last two years, they can then apply for the Scaffolder card.
A qualified Scaffolder can lead a gang on basic scaffold work, as defined in TG20 and the CISRS course content. See our careers page.
Sources: CISRS: Scaffolder-Tube & Fitting, CISRS: Trainee Scaffolder
CITB
Cards and qualifications
The Construction Industry Training Board, the skills and standards body for construction in Great Britain.
CITB: Full definition · used on 3 pages
CITB is funded by a levy on construction employers. It spends the money on training grants, apprenticeships, and occupational standards and qualifications.
It also runs the health, safety and environment (HS&E) test. Passing it is part of getting a construction scheme card.
Sources: CITB: What we do, CITB: About the Health Safety and Environment HS&E test
CSCS card
Cards and qualifications
A card from the Construction Skills Certification Scheme showing that a worker has the training and qualifications for their job on site.
CSCS card: Full definition · used on 1 page
A CSCS card is not a legal requirement. Most principal contractors and major house builders still ask workers on their sites to hold one. To apply, you must pass the right level of CITB health, safety and environment test.
CISRS cards currently carry the CSCS logo. CISRS plans to leave CSCS on 1 June 2027, and cards issued after that will not carry the logo.
Sources: CSCS: About CSCS, NASC: CISRS Announces CSCS Licence Termination to Ensure Inclusive Working Practices
D3 terms
Debris chute
Scaffold components
A chute fixed to the scaffold that carries rubble and waste down into a skip or lorry.
Debris chute: Full definition · used on 1 page
The Work at Height Regulations 2005 ban throwing or tipping material from height where it could injure someone. A chute gives waste an enclosed route to the ground instead.
Councils can set conditions for chutes over a public highway. Westminster, for example, requires the bottom end to be fully enclosed and covered, and the chute to be swung aside when not in use.
Sources: legislation.gov.uk: The Work at Height Regulations 2005, regulation 10, Westminster City Council: Scaffolding
Debris netting
Scaffold components
Mesh fixed to the outside of a scaffold to hold back dust and small pieces of debris.
Debris netting: Full definition · used on 4 pages
Netting stops dust and small debris falling on to people and property below the scaffold.
It also adds wind load. HSE says never to sheet a scaffold or attach netting without telling its designers and erectors. The scaffold must be designed for the extra load. NASC guidance says a netted scaffold needs a design before it goes up, unless a TG20 or TG30 compliance sheet covers it.
Sources: HSE: Scaffolds, NASC: Guide to Appointing a Scaffolding Contractor
Demolition scaffolding
Services and site terms
Scaffolding that gives safe access and contains debris while a building, or part of one, is taken down.
Demolition scaffolding: Full definition · used on 16 pages
Demolition is planned so that debris from any collapse, planned or accidental, stays within an exclusion zone. HSE says a scaffold does not allow that zone to be made smaller. A standard scaffold will not hold a building up during demolition unless it is specifically designed to.
A sheeted scaffold that relies on ties must be lowered as the building comes down, so it does not act as a sail. See our demolition scaffolding page.
Sources: HSE: Demolition, HSE: Structural stability during alteration, demolition and dismantling
E3 terms
Edge protection
Safety and regulations
Guardrails and toe boards fitted along the edge of a roof or platform so people and materials cannot fall off.
Edge protection: Full definition · used on 8 pages
On a flat roof, HSE says a secure double guardrail and toe board around the edge will prevent falls. A sloping roof needs scaffolding to stop people or materials falling, with edge protection at the eaves. On terraced houses that means the back as well as the front.
For construction work, the top guardrail must be at least 950 mm high. See our solar PV scaffolding page.
Sources: HSE: Roof work, legislation.gov.uk: The Work at Height Regulations 2005, Schedule 2
Employers' liability insurance
Permits and paperwork
Insurance that pays compensation if an employee is injured or becomes ill because of their work. Most employers must have it by law.
Employers' liability insurance: Full definition · used on 1 page
The policy must cover at least £5 million and come from an authorised insurer. An employer can be fined £2,500 for every day they are not properly insured. There are some exemptions, for example if you only employ close family members.
Event scaffolding
Services and site terms
Temporary scaffold structures for events, such as stages, grandstands, seating and towers for cameras, lights or speakers.
Event scaffolding: Full definition · used on 13 pages
HSE enforces health and safety for putting up and taking down temporary demountable structures, such as stages and grandstands, at all events.
For speaker and lighting towers, HSE says to plan for wind, ground strength and slope. Any ballast must stay in place while the structure is in use. See our events scaffolding page.
Sources: HSE: Event Safety - Frequently asked questions, HSE: Outdoor equipment to support speaker clusters, lights etc
G1 term
Guardrail
Scaffold components
A rail along the open edge of a platform that stops people falling. On construction work the top rail must be at least 950 mm high.
Guardrail: Full definition · used on 4 pages
For construction work, the Work at Height Regulations 2005 require the top guardrail to be at least 950 mm above the edge. An intermediate guardrail, or a similar barrier, must leave no gap bigger than 470 mm.
Guardrails must be strong enough to stop a fall and to take other loads, such as bricks stacked against brick guards. They must be fixed to something that can carry those loads.
Sources: legislation.gov.uk: The Work at Height Regulations 2005, Schedule 2, HSE: Scaffolds
H3 terms
Haki
Types of scaffold
A system scaffold and weather protection range made by HAKI, a company headquartered in Sweden.
Haki: Full definition · used on 25 pages
HAKI makes its scaffolding and weather protection systems in steel or aluminium at its factory in Sibbhult, Sweden. Its main system, HAKI Universal, is modular and goes together with a hook-on method that needs no tools.
The range includes stair towers, edge protection and the HAKITEC weather protection system. Platforms can use steel planks, timber boards or aluminium planks.
We install Haki alongside traditional tube and fitting. See our Haki system scaffolding page.
Sources: HAKI: System scaffold and weather protection solutions, HAKI: HAKI Universal Scaffold, HAKI: Systems
Harness and lanyard
Safety and regulations
A harness worn by someone working at height and clipped to a secure point with a lanyard, to protect them if they fall.
Harness and lanyard: Full definition
The Work at Height Regulations put collective protection, such as guardrails, ahead of personal protection such as harnesses. In scaffolding, the NASC's SG4 guidance aims to reduce how much scaffolders rely on harnesses and lanyards.
CISRS says a scaffolding labourer may be given a harness to work from a fully boarded platform with a single guardrail. The employer must judge them competent and give them SG4 harness training first.
Sources: legislation.gov.uk: The Work at Height Regulations 2005, regulation 7, HSE: Scaffolding, CISRS: Labourer
HSE
Safety and regulations
The Health and Safety Executive, Britain's national regulator for workplace health and safety.
HSE: Full definition · used on 17 pages
HSE publishes guidance and carries out inspections, investigations and enforcement. Its construction guidance covers scaffolds, towers, roof work and demolition.
For scaffold design and safe working, HSE points to NASC guidance such as TG20 and SG4, and to manufacturers' instructions for system scaffolds.
Sources: GOV.UK: Health and Safety Executive, HSE: About HSE, HSE: Scaffolds
I1 term
IPAF
Cards and qualifications
The International Powered Access Federation, the body for powered access equipment such as mobile elevating work platforms (MEWPs).
IPAF: Full definition · used on 1 page
HSE says MEWP operators should complete a recognised training course and hold a certificate, card or licence. It should list the categories of MEWP they are trained to use, and its expiry date should be checked. HSE links to IPAF in its MEWP guidance.
L2 terms
Listed building
Services and site terms
A building protected by law for its special architectural or historic interest.
Listed building: Full definition · used on 3 pages
In Wales the Welsh Ministers compile the list, with Cadw recommending which buildings go on it. Listing covers the whole building, inside and out, and anything fixed to it.
Changes that affect a listed building's special interest can need listed building consent from the local planning authority, even for minor work. Routine like-for-like repairs do not normally need it. If in doubt, ask the planning authority first, because unauthorised work can be a criminal offence.
Sources: Cadw: Understanding listing, Cadw: Listed building consent
Loading bay
Scaffold components
A strengthened section of scaffold where heavy materials, such as bricks, blocks or tiles, are landed by forklift or crane.
Loading bay: Full definition
A loading bay carries much heavier loads than a normal working platform. HSE says complex loading bays usually need a bespoke design, although TG20:21 covers some standard ones.
NASC guidance says loading bays should have loading bay gates, except where a crane is used. The gate protects workers from the open edge when it is open and stops falls when it is closed. The bay also needs brick guards and a clear sign showing its safe working load.
Sources: NASC: Guide to Appointing a Scaffolding Contractor, HSE: Scaffolds
M1 term
Method statement
Permits and paperwork
A document that sets out step by step how a job will be done safely, with the controls needed at each stage.
Method statement: Full definition · used on 1 page
A method statement is often drawn from the risk assessment. The law requires written arrangements before demolition, dismantling or structural alteration. For most other work it is optional, though HSE notes it is widely used as a planning tool.
HSE says method statements are most useful for higher-risk, complex or unusual work.
Sources: HSE: Administration
P4 terms
PASMA
Cards and qualifications
The association for the mobile access tower industry, which runs training for people who build and use towers.
PASMA: Full definition · used on 1 page
PASMA's Towers for Users course is a one-day course with a practical element. It covers how to assemble, dismantle, alter, move and inspect mobile access towers. The qualification usually lasts five years.
Sources: PASMA: Home, PASMA: Towers for Users
PPE
Safety and regulations
Personal protective equipment, such as safety helmets, safety footwear, high-visibility clothing, gloves and harnesses.
PPE: Full definition · used on 2 pages
PPE protects against hazards that remain after other controls, such as engineering controls and safe systems of work, are in place. Employers must provide it wherever a risk cannot be adequately controlled in other ways.
Workers cannot be charged for PPE used only at work. Employers must provide it free of charge if a risk assessment shows it is needed.
Sources: HSE: Using personal protective equipment (PPE) to control risks at work, HSE: Do employers have to provide personal protective equipment (PPE)?
Protection fan
Scaffold components
A protective structure on the outside of a scaffold that catches falling material before it reaches people below.
Protection fan: Full definition
Fans are used where material could fall on to a pavement, road or other public area. Westminster City Council, for example, requires fans or screens wide enough to give the public complete protection.
Haringey Council advises putting fans, crash decks and tunnels in place as early as possible. HSE adds that fans can help deter people from climbing a scaffold.
Sources: Westminster City Council: Scaffolding, Haringey Council: Safely putting up and taking down scaffolds, HSE: Preventing unauthorised access onto scaffolding and other work platforms
Public liability insurance
Permits and paperwork
Insurance that covers a business for claims made against it by members of the public.
Public liability insurance: Full definition
The law does not require it, unlike employers' liability insurance. Councils such as Torfaen and Carmarthenshire ask for proof of at least £10 million of cover before they issue a scaffold licence.
Sources: Companies House: What insurance does a small business need?, Torfaen County Borough Council: Scaffolding & Hoarding Permits, Carmarthenshire County Council: Scaffold licence
R1 term
Risk assessment
Permits and paperwork
A check of what could cause harm on a job, how likely and serious that harm is, and what will be done to control it.
Risk assessment: Full definition · used on 5 pages
Employers must make a suitable and sufficient assessment of the risks to their employees and to anyone else affected by their work. Employers with five or more employees must record the significant findings.
In scaffolding, the risk assessment and method statement are often issued together as RAMS. The NASC publishes guidance on RAMS for scaffolding contractors.
Sources: legislation.gov.uk: The Management of Health and Safety at Work Regulations 1999, regulation 3, HSE: Managing risks and risk assessment at work, NASC: Guide to Appointing a Scaffolding Contractor
S16 terms
Scaffold board
Scaffold components
A timber plank, 225 mm wide, laid across the scaffold to make the working platform.
Scaffold board: Full definition · used on 1 page
Timber scaffold boards must meet BS 2482:2009. It covers boards 225 mm wide and either 38 mm or 63 mm thick, graded by how far apart their supports can be.
A working platform must be fully boarded and at least 600 mm wide. A board should not overhang its last support by more than four times its thickness. Short boards, and boards exposed to high winds, should be fixed down.
Sources: BSI: BS 2482:2009 Specification for timber scaffold boards, HSE: Scaffolds, NASC: Guide to Appointing a Scaffolding Contractor
Scaffold design
Permits and paperwork
The drawings and calculations for a scaffold that falls outside the standard set-ups in TG20 or the manufacturer's guidance.
Scaffold design: Full definition · used on 8 pages
A scaffold must either follow a recognised standard configuration or be designed by calculation by a competent person. HSE lists structures that normally need a bespoke design, including temporary roofs, staircases and cantilevered scaffolds.
Design drawings should show every tie position and the type of tie needed. Copies of designs or compliance sheets go to the customer and are kept on site.
Sources: HSE: Scaffolds, NASC: Guide to Appointing a Scaffolding Contractor
Scaffold handover
Permits and paperwork
The point when a finished scaffold is inspected and formally passed to the customer, with a handover certificate.
Scaffold handover: Full definition · used on 7 pages
Until handover, a scaffold should display a 'do not use' notice. The scaffolding contractor's inspector checks the finished scaffold against the regulations and its design or TG20 compliance sheet. They then complete a Scaffold Handover Certificate.
The customer gets a copy, along with any design drawings or compliance sheets and the tie test records. NASC guidance treats the handover certificate as the first inspection.
Scaffold inspection
Safety and regulations
A check by a competent person that a scaffold is safe. It is needed before first use, at least every 7 days, and after anything that could affect it.
Scaffold inspection: Full definition · used on 8 pages
A scaffold used for construction work, where someone could fall 2 metres or more, must be inspected once it is put up and before use. It must then be inspected at least every 7 days, and again after events such as high winds or an alteration.
The inspector writes a report before the end of the working period and hands it over within 24 hours. The report stays on site until the work is finished, then at an office for three months.
The hirer or user of the scaffold is responsible for the 7-day inspections. Tag systems help, but they do not replace the written report.
Sources: legislation.gov.uk: The Work at Height Regulations 2005, regulation 12, HSE: Inspection and reports (CIS47), NASC: Guide to Appointing a Scaffolding Contractor
Scaffold licence
Permits and paperwork
Permission from the highway authority, usually the council, to put scaffolding on or over a public pavement or road.
Scaffold licence: Full definition · used on 4 pages
Section 169 of the Highways Act 1980 requires a licence for scaffolding that obstructs a highway during building work. The holder must light the scaffold at night and follow the authority's directions on traffic signs. A scaffold kept entirely on private land does not need one.
Councils set their own conditions. Torfaen issues permits to the company doing the work and asks for at least 24 hours' notice. Carmarthenshire asks for proof of £10 million public liability insurance. We help clients apply.
Sources: legislation.gov.uk: Highways Act 1980, section 169, Torfaen County Borough Council: Scaffolding & Hoarding Permits, Carmarthenshire County Council: Scaffold licence
Scaffold sheeting
Scaffold components
Plastic sheeting fixed around a scaffold to keep the weather out and dust in.
Scaffold sheeting: Full definition · used on 8 pages
Sheeting lets work carry on in wind and rain and keeps dust inside the work area. Monarflex is one brand of flame-retardant scaffold sheeting. Wrapping a whole building in sheeting or netting is often called encapsulation.
A sheeted scaffold catches much more wind, and the ties pass that load to the building. The scaffold must be designed for sheeting before it goes on. During demolition, a sheeted scaffold that relies on ties must be lowered as the building comes down.
Sources: HSE: Structural stability during alteration, demolition and dismantling, HSE: Scaffolds, BMI: Monarflex Super T Plus Firesmart
Scaffold tower
Types of scaffold
A freestanding tower, often on castors, with a small working platform for short jobs at height.
Scaffold tower: Full definition · used on 4 pages
Towers must be put up by trained, competent people following the manufacturer's instruction manual, including any stabilisers or outriggers. They need firm, level ground, double guardrails and toe boards.
Castors stay locked while the tower is in use. Nobody should be on a tower while it is moved, and towers should not be used in strong winds.
For construction work where someone could fall 2 metres or more, a tower is inspected after assembly and every 7 days. PASMA runs the Towers for Users course for people who put up and use towers.
Sources: HSE: Tower scaffolds, PASMA: Towers for Users
Scaffolding labourer
Cards and qualifications
A worker who supports scaffolders on site but is not allowed to erect, alter or dismantle scaffolding.
Scaffolding labourer: Full definition · used on 9 pages
The CISRS Labourer card covers labouring and driving work in support of scaffolding, from a safe and secure position. To get it, you need the CISRS Operative Training Scheme (COTS) course and a CITB HS&E test from the last two years. The card lasts five years.
NASC guidance expects anyone doing these duties to hold an in-date labourer card. See our careers page.
Sources: CISRS: Labourer, CISRS: FAQs, NASC: Guide to Appointing a Scaffolding Contractor
Scaffolding lift
Scaffold components
A powered hoist fitted to or beside a scaffold to raise materials, such as solar panels, to the working level.
Scaffolding lift: Full definition · used on 2 pages
NASC guidance lists mechanical hoists among the preferred ways to reach a scaffold on larger projects, ahead of ladders.
Hoists are lifting equipment under the Lifting Operations and Lifting Equipment Regulations (LOLER). A competent person must thoroughly examine them every 12 months, or every 6 months if they lift people. A written examination scheme can set different intervals.
Sources: NASC: Guide to Appointing a Scaffolding Contractor, HSE: Thorough examinations and inspections of lifting equipment, HSE: Lifting Operations and Lifting Equipment Regulations (LOLER)
SG4
Safety and regulations
The NASC's guidance on preventing falls while scaffolds are put up, altered and taken down. The current edition is SG4:22.
SG4: Full definition · used on 1 page
HSE points scaffolders to SG4 for erecting, altering and dismantling scaffolds safely. It puts collective fall protection first, which cuts the time scaffolders spend relying on harnesses and lanyards.
SG4:22 is aimed mainly at people who manage scaffolding work. It keeps its core method of working, known as the Scaffolders' Safe Zone.
Sources: NASC: SG4:22 Preventing Falls in Scaffolding Operations, HSE: Scaffolding
SMAS Worksafe
Safety and regulations
A health and safety accreditation for contractors from Smas Worksafe, one of the assessment schemes under SSIP.
SMAS Worksafe: Full definition · used on 17 pages
Smas Worksafe assesses a contractor's health and safety documents, such as its policy, risk assessments, method statements and training records. The assessment follows the SSIP core criteria, and the certificate lasts 12 months.
Other SSIP schemes recognise the certificate, so a contractor does not have to repeat the same assessment for each client. Square Scaffolding Limited is SMAS Worksafe accredited. See our health and safety page.
Sources: Smas Worksafe: SSIP Certification, SSIP: Simplifying procurement
Solar PV scaffolding
Services and site terms
Scaffolding and edge protection that let installers fit solar panels on a roof safely and get the panels up to it.
Solar PV scaffolding: Full definition · used on 16 pages
HSE says a sloping roof needs scaffolding to stop people or materials falling from the edge, with edge protection at the eaves. On terraced houses that means the back as well as the front. See our solar PV scaffolding page.
Sources: HSE: Roof work
Sole board
Scaffold components
A timber board laid under the base of a scaffold or tower to spread its weight on soft or uneven ground.
Sole board: Full definition
A scaffold needs a firm, level base that can carry the scaffold and everything on it. Soft ground, drains and basements underneath should be checked before building starts.
Sole boards go under base plates, or under the castors of a mobile tower, to give a firmer footing. PASMA says castors must not be used on soft ground without them.
SSIP
Safety and regulations
Safety Schemes in Procurement, the umbrella body for health and safety assessment schemes such as SMAS Worksafe and CHAS.
SSIP: Full definition · used on 1 page
SSIP's member schemes assess contractors against a shared set of core criteria. The aim is to stop suppliers having to repeat the same health and safety pre-qualification for every client.
Sources: SSIP: Simplifying procurement, Smas Worksafe: SSIP Certification, CHAS: The UK Leader in Compliance & Risk Management
Stair tower
Types of scaffold
A temporary staircase built from scaffold parts, giving safer access to a scaffold than ladders.
Stair tower: Full definition · used on 2 pages
NASC guidance sets an order of preference for getting on and off a scaffold. Temporary staircase towers come after permanent stairs and mechanical hoists, and before ladder access.
HSE lists staircases among the structures that normally need a bespoke design. HAKI makes stair towers for construction sites.
Sources: NASC: Guide to Appointing a Scaffolding Contractor, HSE: Scaffolds, HAKI: Systems
System scaffold
Types of scaffold
A scaffold built from a manufacturer's purpose-made parts, such as Haki, instead of loose tubes and couplers.
System scaffold: Full definition · used on 10 pages
Each system has its own parts and connections. It must be put up and tied following the manufacturer's instructions, or the NASC's TG30 guidance for system scaffolding. Anything outside that guidance needs a specific design.
Scaffolders need training on the particular system, and CISRS runs product training for system scaffolds. See our Haki system scaffolding page.
Sources: HSE: Scaffolds, NASC: Guide to Appointing a Scaffolding Contractor
T7 terms
Temporary roof
Types of scaffold
A roof built on scaffolding over a building, so work can carry on in the dry while the real roof is open.
Temporary roof: Full definition · used on 8 pages
A temporary roof keeps the building and the people working on it dry while the roof is open. HSE lists temporary roofs among the structures that normally need a bespoke design.
Larger spans often use a purpose-made system, such as HAKI's HAKITEC weather protection. A temporary roof catches a lot of wind, so it must be secured to resist it. See our Haki system scaffolding page or contact us.
Sources: HSE: Scaffolds, HAKI: Systems, Westminster City Council: Scaffolding
TG20
Safety and regulations
The NASC's guide to good practice for tube and fitting scaffolding. The current edition is TG20:21.
TG20: Full definition · used on 2 pages
TG20 covers standard tube and fitting structures, including independent scaffolds, putlog scaffolds, birdcages, chimney stack scaffolds and some loading bays. Older paperwork may refer to TG20:13, an earlier edition.
When a scaffold fits TG20, the scaffolder can issue a TG20 compliance sheet. Anything outside its scope needs a design with calculations from a competent scaffold designer. System scaffolds follow the manufacturer's guidance or the NASC's TG30 instead.
Sources: NASC: TG20:21 Operational Guide, NASC: Guide to Appointing a Scaffolding Contractor, HSE: Scaffolds
Tie
Scaffold components
A fixing that holds a scaffold to the building. Most scaffolds stand on their own legs but rely on ties to stop them moving sideways.
Tie: Full definition · used on 5 pages
A standard scaffold carries its own weight down to the ground, but it must be tied to the building for sideways support. Each tie has to stay within its safe working load.
Ties go in as the scaffold goes up and come out in stages as it is taken down. If a tie has to be moved so work can carry on, an equivalent tie must be fitted nearby.
Anchors drilled into masonry for ties are pull tested with a purpose-made tester. NASC guidance asks for at least three tests per scaffold, or 5% of the ties if that is more.
Sources: HSE: Scaffolds, HSE: Structural stability during alteration, demolition and dismantling, NASC: Guide to Appointing a Scaffolding Contractor
Toe board
Scaffold components
An upright board along the edge of a working platform that stops tools and materials rolling or being kicked off.
Toe board: Full definition
Toe boards run along the open edges of a platform, at the foot of the guardrails. For construction work, the Work at Height Regulations 2005 require them to be suitable and sufficient to stop people, materials and objects falling.
With a main guardrail and an intermediate guardrail above, they make up the usual edge protection on a scaffold platform.
Sources: legislation.gov.uk: The Work at Height Regulations 2005, Schedule 2, HSE: Scaffolds
Trainee scaffolder
Cards and qualifications
Someone working towards the CISRS Scaffolder card, who must work under the direct supervision of a qualified scaffolder.
Trainee scaffolder: Full definition
The Trainee Scaffolder card follows at least three months on a CISRS Labourer card. Training covers CISRS Part 1 and Part 2, an NVQ Level 2 and a one-day skills test. All of it must be finished within two 18-month trainee cards.
See our careers page.
Sources: CISRS: Trainee Scaffolder
Trunk road
Permits and paperwork
A major A road that, in Wales, the Welsh Government is responsible for. Scaffolding beside one may need permission from a different highway authority than the council.
Trunk road: Full definition · used on 1 page
The Welsh Government is responsible for about 1,516 km of trunk roads and 178 km of motorway in Wales. Two trunk road agents run and look after these roads for it.
A scaffold licence comes from the highway authority for the road in question. We check which authority applies before we apply.
Sources: Welsh Government: How we manage the roads we own, legislation.gov.uk: Highways Act 1980, section 169
Tube and fitting
Types of scaffold
Traditional scaffolding built from steel tubes joined with couplers, which scaffolders also call fittings.
Tube and fitting: Full definition · used on 11 pages
NASC guidance says scaffold tube must be galvanised steel to BS EN 39 type 4, or high tensile steel tube. The couplers must meet current UK industry standards.
Common set-ups are covered by the NASC's TG20 guide to good practice for tube and fitting scaffolding. Anything outside TG20 needs a design with calculations from a competent scaffold designer.
Sources: NASC: Guide to Appointing a Scaffolding Contractor, HSE: Scaffolds
W1 term
Work at Height Regulations 2005
Safety and regulations
The main law in Great Britain on preventing falls at work, including falls from scaffolding.
Work at Height Regulations 2005: Full definition · used on 1 page
Employers must avoid work at height where the job can reasonably be done safely without it. Where it cannot, they must use equipment and measures that prevent falls. If a risk of falling remains, they must reduce the distance and consequences of a fall.
When choosing equipment, collective protection such as guardrails comes before personal protection such as harnesses. The regulations also require scaffolds used for construction work to be inspected at least every 7 days.
Sources: legislation.gov.uk: The Work at Height Regulations 2005, regulation 6, legislation.gov.uk: The Work at Height Regulations 2005, regulation 7, legislation.gov.uk: The Work at Height Regulations 2005, regulation 12
Nothing here matches that. Try fewer words.
Enquire About Residential Scaffolding Today!
Whether you're planning a roof repair, a fresh coat of paint, or a full extension - Our team have the experience and local knowledge to keep your home project safe and on track!
- Monday - Sunday 8am to 6pm
- Call us for an appointment
- 0333 242 1461
- enquiries@squarescaffolding.com
- 12 Corporation Road, Newport, NP19 0AR